Holidays and employee costs: where the numbers come from
Two numbers quietly shape a lot of what Current shows you: the company holiday calendar (which drives every schedule) and each employee's internal hourly cost (which drives every margin figure). Both can come from two places — synced from Autotask, or entered by hand in Current — and it matters which one applies where. Here's exactly how each works, verified against the code, not guessed.
Holidays: one calendar per tenant, two ways to fill it
Current keeps a single company-wide holiday calendar shared by every project — this is what "weekends + holidays skipped" on the Timeline actually skips. It's filled two ways, and both can be in play at once:
- +Synced from Autotask — Current's regular sync pulls Autotask's company holiday set and adds those dates automatically. These rows are tagged as coming from Autotask. (Autotask workspaces only.)
- +Added manually — a Tenant Admin can add a one-off holiday (a date plus an optional name) directly in Current, for anything your PSA doesn't have — or, on ConnectWise, for the whole calendar.
- 1Open Settings → HolidaysAdmin-only page. It shows a running count, e.g. "14 holidays — 10 synced from Autotask, 4 added here."
- 2Review each entryA synced holiday shows an Autotask badge (hover it: "reappears on next sync if deleted here"). A manual one shows a pen icon instead.
- 3Add a manual holidayPick a date, optionally name it, and save. It applies to every project in the tenant immediately.
- 4Delete carefullyDeleting a synced holiday works, but it comes back on the next Autotask sync — delete it in Autotask instead if you want it gone for good.
Employee cost: per-person, from two sources, admin-only
Every person can have an internal hourly cost — what they actually cost the business per hour, as opposed to what you bill a partner. Current uses this only for the Profitability lens on Reports; it never appears anywhere a project manager, engineer, or partner viewer can see.
- +Synced from Autotask — if a person is linked to an Autotask resource, their Internal Cost (Burden Rate) is pulled in automatically on every sync. Current shows this as the source and won't let you hand-edit it, because the next sync would just overwrite your edit. (Autotask workspaces only.)
- +Entered manually — for anyone without a synced cost (including everyone on a ConnectWise workspace), a Tenant Admin can enter a rate by hand.
What holidays and costs are each used for
| Data | Drives | Doesn't drive |
|---|---|---|
| Holiday calendar | Task scheduling and critical-path dates on the Timeline, Dependency map, What-if, and the Schedule grid. Also, on a workspace measuring response times on working hours, the average first response and average resolution time on your dashboards: a holiday is not a working day, so it is left out of both | Cost, margin, or budget figures. Nor SLA compliance, which is your PSA's own verdict against its own due times and its own calendar |
| Employee hourly cost | The Profitability / Margin lens on Reports (revenue minus internal labor cost, by project) | Scheduling, capacity, or the standard project budget/burn view — those use billable rate and hours, not cost |
See "PTO and availability-aware scheduling in the Timeline" for how the holiday calendar interacts with individual PTO, and see "Roles & permissions: who sees what" for the full admin-only visibility list.