Show a partner when a task is waiting on them

Mark a task as waiting on the partner, with a short note. Their portal shows it under Waiting on you, with how long it has waited and the go-live effect.

Updated 3 min read
On this page · 3 sections

When a task can't move until the partner answers a question or makes a decision, mark it as waiting on them. The partner sees it at the top of the project in their portal, under "Waiting on you", with the note you wrote, so they know the next step is theirs.

Mark a task as waiting

  1. 1
    Open the task
    Open the task from the project, the Kanban board or My Day. The card "Waiting on the partner" sits under the description (it uses your workspace's own word for the businesses you serve).
  2. 2
    Write what you need
    Press "Mark as waiting on the partner" and write what you need from them, in 280 characters or fewer. The partner reads it word for word, so write it to them: "Which handset do you want for the front desk?"
  3. 3
    Set when the wait began
    "Waiting since" starts at today. Move it back if you have been chasing for a while; it can't be in the future or more than a year ago.
  4. 4
    Save
    The task now shows in the portal. Edit the note at any time, or press "No longer waiting" when the answer arrives.

What the partner sees

  • The task name and your note.
  • How long it has waited: "Waiting since Nov 3, 2026 (7 days)."
  • On a task marked critical: "Each day this waits can move the go-live date (Dec 1, 2026) by a day." The date is the project's due date. On any other task they see only how long it has waited.
  • A line asking them to reply in the project conversation or to their project contact.

They never see who marked it, and they only ever see tasks on projects shared with them. The section is absent when nothing is waiting, and a completed task drops out of it by itself.

Tip
Make the go-live line show
The go-live line follows the task's Critical switch in the task drawer. Mark the task critical when it sits on the path to go-live, so the partner sees what a slow answer costs.

Who can mark a task

A tenant admin, a service manager or a project manager can mark any task. An engineer, a dispatcher or a vCIO can mark a task assigned to them. Everyone else on your team sees the note in the task drawer but can't change it. A portal user can only read it.

Note
It stays in Current
The wait is kept in Current only. Nothing is sent to your PSA, so it works the same on PSA-synced projects and on projects that live only in Current, and it never changes the task's status.